How Do You Manage Customer Change Orders? Three Suggestions

Situation: A mid-sized company has taken over management of the supply chains for several large customers. The products that the company manufactures have long lead times both for sourcing materials and manufacturing customer orders. Sometimes customers either ask for additional production on an existing order in process, or ask for deliveries to be spread beyond contracted timelines. Either situation has a significant impact on the cost of producing the order and company profitability. How do you manage customer change orders?

Advice from the CEOs:

  • The issue is one of managing contracts and customer expectations. Because this is hurting the company, prime the customers now that things will need to change in the future. Depending upon the level of comfort the response can be reactive or proactive.
  • A proactive response: because this happens with some frequency, establish a change order schedule and share this with the customers. Your message will be that you are happy to accommodate changes in orders, but you need to recover the cost of these changes in order to be able to continue supplying the customer. Include the change order schedule in future customer purchase contracts. This may cause them to have second thoughts about requesting changes in orders.
  • A reactive response: the next time a customer makes these demands the response can be: “We’ll take care of you this time but when we draft our next contract we have to adjust the terms of the contract so that it is a win-win.”
  • The appropriate response depends on value of each customer’s business to the company – both revenue and profit – and your confidence in the relationship with the customer.

[like]

How Do You Simplify a Firm-wide Software Roll-out? Five Ideas

Situation: A company plans to implement a new CRM system. They have a project road map and have assigned a manager for the implementation. However, the CEO has concerns because this is the most significant software roll-out that the company has ever attempted. She wants to assure that the roll-out proceeds smoothly, and that and that sales, marketing and customer service functions are not hampered. How do you simplify a firm-wide software roll-out?

Advice from the CEOs:

  • Focus on company business objectives as you plan and implement the roll-out. Optimize the system to company business objectives, not just what the team wants.
  • Scope this out as a project management exercise.
    • Identify objectives.
    • Build and test.
    • Roll the system out to preliminary production and collect feedback on functionality.
    • Rebuild and test.
    • Plan and conduct system orientation training.
    • Set a date for the roll-out.
  • Don’t immediately roll the new system out company-wide. Conduct an initial implementation with a small scale test team. Make sure that everything works as planned and that day-to-day function is not compromised. From the information that you gather during initial implementation, tweak orientation training so that everyone is comfortable with the new system.
  • During initial planning sessions to set system objectives, meet first with managers whose teams will be impacted by the roll-out. Managers may not speak freely if their support staff are present.
  • Have a roll-out celebration and be generous complimenting personnel who have been involved in planning and roll-out.

[like]

How Do You Focus Managers on Growth? Five Suggestions

Situation: Two key managers of a company are too busy with day-to-day activities to focus their planned 40% of time on growth. The company has hired personnel to relieve some pressure on them, and a new ASP (Application Service Provider) is improving customer out-reach. How can the CEO take pressure off these managers so that they have time to grow the business? How do you focus managers on growth?

Advice from the CEOs:

  • Small companies grow through their early stages with everyone wearing many hats and doing everything. The company is now larger than this and it has to stop. Managers need to focus their responsibilities where you need them to focus and stop doing less important tasks.
  • Have you gone over key responsibilities and expectations for the two managers? Do they have clear objectives and deliverables? If not, focus on this.
  • Brainstorm with them how they could free-up time to focus on growth.
    • Do this in a meeting. Your plan is 10% growth. Ask for their ideas on how to grow the business, and develop a plan to put their ideas into action. What help or resources do they need to meet this plan?
    • Three heads better than one to ask core questions – let them come up with the answers.
  • Design processes to address needs and responsibilities.
    • Rank implementation of options in terms of impact to the company and financial results.
    • Given the ranking, implement programs sequentially – most relevant and easiest first.
  • Taking orders by phone is clerical. This should not be a manager’s prime focus.
    • Have a clerical person answer the phone, and train them over time.
    • Limit the manager’s direct involvement in phone orders to critical situations.

[like]

How Do You Optimize a Promotion? Four Recommendations

Situation: A company has a long-term employee who has been growing in responsibility as Customer Service Supervisor. The CEO is considering giving this employee the new title of Production Manager at the same time that the employee receives an annual wage increase. How do you optimize a promotion?

Advice from the CEOs:

  • Any promotion or increase in responsibility must be consistent with the strategic direction of the company. What are the company’s current and future needs and, based on past performance, can this individual satisfy those needs? If so, this may be a good match.
  • In addition, it is important to consider the needs and career path of the individual. Does the new position involve an increased time commitment, additional skills and training, or other important factors, and is the individual prepared for this increased commitment? Will a higher level of commitment be rewarded financially? The only way to answer these questions is to have a conversation with the individual.
  • If as the first two questions are considered there is any doubt, a longer-term transition may be appropriate. Meet with the Customer Service Supervisor and set a series of goals and objectives that will demonstrate their ability to assume the new role over a 6 month time frame. The concept here is that you must work at the level of the new job before you get it.
  • Before embarking on the above recommendations, draft a job description and list of responsibilities for the new Production Manager position, consistent with the company’s needs as it grows. This will involve input from employees who currently handle these responsibilities. Also look at the reporting structure as it currently exists and as it may change.

[like]

How Do You Close the Books on Time? Four Suggestions

Situation: A company has experienced delays in closing their annual books for years. Inability to complete final inventory is the critical factor. In recent years it has taken four months or more to get final numbers for the year. How do you close the books on time?

Advice from the CEOs:

  • It is important to put a system into place well in advance of fiscal year end. A key part of this is to conduct final inventory so that it is done smoothly and accurately either immediately prior to or following the end of the fiscal year. Retail or wholesale operations normally complete final inventory within 30 days of fiscal year end.
  • If your inventory includes both large and small value items, ask whether you have to count everything. Based on past inventory it may be that small items that do not substantially impact final inventory can either be eliminated from the count or handled on an exception basis.
  • Consider a system of doing monthly or rotating monthly inventory smaller sets of items that make up perhaps 60% of sales, and quarterly inventory on an additional larger set of items that together with the first groups make up perhaps 80% of sales. By completing inventory of these items more frequently, the company will not only have a better handle on total inventory, but is also likely to be more accurate at the end of the year. At year-end inventory add those items that make up the final 20% of sales to the inventory count.
  • Again, depending upon the nature of the inventory, it may not be necessary to count items that, as groups, are valued under $500 per group. Seek expert advice from your accountant on this point.

[like]

How Do You Move a Live Online Data Center? Seven Suggestions

Situation: A company has run out of space and is planning a move to a new and larger facility. The biggest challenge is that they maintain a live online data center upon which their clients depend. How do you move a live online data center?

Advice from the CEOs:

  • This is not a rare event. Many companies with live online data centers have to upgrade their systems on a regular basis as equipment and software technologies evolve. Maintaining service during a move is not significantly different. Research what steps these companies have taken to minimize disruption during upgrades.
  • Don’t try to do it all by yourself. Seek outside expertise to help you plan the move, and to develop options that will minimize both downtime and service interruption.
  • Ask a trusted data center resource for a 3rd party audit of your move plan.
  • When one company moved, they overlapped their leases by one month, and their Internet connections by 2-3 months. This gave them breathing room as they completed the move and allowed them to stay live uninterrupted through the move.
  • Another company increased their back up servers and service. They also planned their move to occur during what they knew would be a low demand block of time. As a result, they were able to complete the move, plug in the servers and were only down for 30 minutes.
  • If it is feasible, consider leaving your old center in place as a back-up data center.
  • Conduct a number of practice shutdowns and restarts to test your systems.

[like]

How Much Inventory Should You Carry? Six Considerations

Situation: A company has been offered the opportunity to buy a container of raw material from China at what may be a favorable price compared to local supply. This raw material will last 6-12 months at current and anticipated production rates. Does it make sense to purchase 6-12 months of raw material inventory in advance? How much inventory should you carry?

Advice from the CEOs:

  • This is a fairly straightforward economic question. What are the risks and costs of purchasing this large lot of inventory vs. purchasing month-to-month? Here are the factors to include in your evaluation:

o    What is the cost difference of a container versus local supply?

o    Another option is to commit in advance to 6-12 months’ supply from the current supplier. What pricing will the local supplier offer for committed regular purchases?

o    How many months of inventory are required if you need to change suppliers?

o    What is the viability of the local vs. the foreign supplier? If you cease purchasing from the current supplier for 6-12 months will they remain a viable supplier? Similarly, can you count on the foreign supplier long-term?

o    What is your cost of capital, and what is the tax effect of significant inventory at the end of the tax year?

o    If you purchase a container, what is the exposure to overstock of certain sizes of product? What is the carrying cost of this overstock?

  • Do the numbers and negotiate between the two suppliers.

Category: Manufacturing & Operations

Key Words: Inventory, Purchase, Advance, Container, Carry, Cost, Commit, Supplier, Tax, Negotiate

[like]

How Do You Optimize Supply Agreements? Seven Guidelines

Situation: A company wants to add off-shore manufactures to its supply chain. This is a new experience and the CEO seeks guidance on how to negotiate supply agreements. They want win-win agreements with their new suppliers. How do you optimize supply agreements?

Advice from the CEOs:

  • No supplier relationship is risk-free, especially if you are a small company. Be sure to cover ownership of new IP developed during the relationship. For example, assure that the supplier adds no new developments without communicating these to you in writing. You may want to fund new developments selectively to assure protection of your IP. This is essential if you need to switch or add suppliers rapidly to maintain adequate supply.
  • A service agreement is not always about cost. It’s about deliverables, and quid pro quo is important.
  • Manage your key supplier relationships as diligently as you manage your key client relationships. They are equally critical.
  • In a contract negotiation between supplier and OEM or customer, both sides need to clarify customer needs and supplier capabilities. The greater the transparency on expectations, deliverables, and contingencies, the better the agreement and contract.
  • In negotiating an agreement with a Chinese company, make the enforcement jurisdiction either Hong Kong or Macao. Why? So that courts can enforce terms of the agreement on the Chinese party in the case of a dispute.
  • Post-termination obligations are a key to any negotiation – you want this clarified in advance.
  • Contracts serve two purposes: a legal tool, and a way to drive behavior. They provide an opportunity to assure that both parties are on the same page and, under the best circumstances, serve as process documents.

Special thanks to Bijan Dastmalchi of Symphony Consulting for his contribution to this discussion.

[like]

Do LEAN and Six-Sigma Work for Services? Three Thoughts

Situation: A professional service company is intrigued by LEAN and Six-Sigma approaches to increasing production efficiency and reducing costs. Most of the examples that they see of LEAN and Six-Sigma in action are in production or manufacturing settings. Do LEAN or Six-Sigma programs apply to processes in a professional services environment?

Advice from the CEOs:

  • LEAN and Six-Sigma are heads-down approaches to process improvement.  In a customized solution environment, standardization of processes has less pay-off. As an alternative, consider Agile Development and similar heads-up process solutions.
  • Agile Development is both a philosophy and a process. Steps to introducing Agile Development to a professional services environment include:
    • Identifying high risk areas of individual project plans,
    • Double resourcing high risk areas to increase the likelihood of fast, satisfactory solution outcomes,
    • Looking for collaborative synergies and scenarios,
    • Scheduling regular team meetings to enhance collaboration,
    • Working opportunistically rather than systematically to increase efficiency, and
    • Using project post-mortems to refine systems and processes.
  • One professional services company which has adopted Agile Development assigns Senior Engineers as outside consultants on projects. These individuals bring a more experienced perspective, and can identify more efficient ways to find solutions and produce a more cost effective and timely result.

[like]

Can Bonus Plans Differ Between Departments? Four Thoughts

Situation: A CEO wants to build a new bonus program for the company’s professional services team. He wants to include a customer satisfaction component, because the group is historically weak in this area. Does it make sense to have a different bonus plan for professional services personnel and managers than for product development personnel and managers? Can bonus plans differ between departments?

Advice from the CEOs:

  • Many companies have different bonus structures for different departments. This is natural because different departments have different functions. For example, Sales may evaluated for bonuses based on a combination of revenue and gross margin achievement, while Finance is evaluated on profitability and Product Development is evaluated on hitting product launch schedules and new product sales.
  • Changing bonus structures can be a sensitive matter. If the team impacted is not included in the process of drafting the new plan, changes may be perceived as negative. If this is the case, it’s better to frame the new program so that you limit your commitment to it to just one year, and let the team know that this may change this next year.
  • How do you go about including customer satisfaction surveys as a component of bonus calculation?
    • If you want to use customer satisfaction as part of the plan, benchmark customer service satisfaction before you launch the plan. If you don’t benchmark, how do you know whether performance improves?
    • Survey response rates will be an issue – you won’t get 100% and may get a survey response rate of 10% or worse. Be prepared for this and make sure that data with a low response rate will support your objectives.
    • A survey is a lagging metric. If you can find a measurable leading metric to use as well this is better.
    • Be careful of how the survey is drafted and who conducts it. Both can bias results.
  • As an alternative to making customer satisfaction part of a bonus plan, consider starting a customer satisfaction or loyalty program. The most important question to ask will be: would you recommend us to your peers?  Any low response guarantees a follow-up call from the company.