How Is The Economy Impacting Your Sales Plan? Five Views

A company is revising sales forecasts for 2016 and seeks the advice of others. A combination of low energy prices and shaky financial markets sparked by the Chinese decline has left many questioning whether they should revise their plans to account for an economic contraction. How is the economy impacting your sales plan?

Advice from the CEOs:

  • Niche Software Company – we are coming off of a good year. Our industry has seen low impact so far. Going forward we are cautiously optimistic. A couple of clients have delayed projects but didn’t cancel.
  • Services Company – hiring has been frozen. Adjustments to staff count have already been made. Clients are asking us to contact them again early in the second quarter. Opportunities exist in the health care area.
  • Hardware Company – we are running scared. We have cut business and personnel expenses to assure survival. A large customer just announced new plant construction earlier this week – this may help to turn things around. We are assuming this will be mean a longer term rather than a short-term opportunity.
  • Niche Software Company – cutting personal/business expenses. Long term things look favorable, but we have to survive the short term. Attendance at a large trade show this month was a little above last year but we don’t know whether this will yield a significant increase in sales.
  • Trades – Projects with big bank backing are on hold. We see large scale bidding wars for projects. Where there used to be 3-5 bids there are now 15 or more. Looking for consolidation of competition – especially union–based shops.

How Do You Help Managers Think Bigger? Four Guidelines

Situation: A company is transitioning from a time and materials to a fixed price bid model. Estimators and project leads find this transition difficult. We need them to think like business managers. How do you help managers to see and think in terms of the big picture?

Advice from the CEOs:

  • First, set up a framework that repositions projects in a business framework.
    • All projects are business go/no decisions with expenses, minimum profitability targets, and incentives provided for beating initial projections.
    • This will help generate more consistency in bids and final gross margins per project.
  • Next, teach managers and employees industry and company standards within your new model.
    • Do post-mortems on all projects. Did we make or lose money versus initial estimate? How much? How did we perform against estimated time and expense? Were client expectations met? Were they exceeded? What was good or bad about the project? Were there errors in the original estimates? Where could we have saved cost?
    • Use this information to improve your estimating process over time.
  • You have a long history of T&M projects. Categorize these by project type. Look at the hours required to complete the projects – both engineering and management time – as well as other costs. Establish range and averages within each category.
    • Look for key variables among the project categories: scope of project, learning curves, efficiency of team members.
    • Work through known costs and outcomes on past projects as examples to teach the process.
    • For new projects, calculate best, medium and worst case hours and costs. Bid based on your worst case as you develop your learning curve.
    • Make sure to include a project management fee on top of your T&M estimates. Eventually you want to develop an overhead percentage to cover project management.
  • Team your estimator with the project lead both for project input, and performance against the bid.
    • Evaluate and compensate both based on project outcome.
    • The critical measure will be gross margin generated versus gross margin estimated on the project.

Key Words: Leadership, Project, Time and Materials, Fixed Price, Bid, Framework, Consistency, Standards, Variables, Estimator, Lead, Incentive